Medical Center — Interior Partition Walls (Shrek Medical Offices)

Latest Bid

$40,715

Square Footage

1,420

Units

Scope Class

Drywall Only

Plan Stage

Project Lifecycle

Received
Takeoff
Bidding
Submitted
Awarded
Start

Notes & Correspondence

Adding a note also updates last-correspondence date for this project.

No notes yet.

Project Brief

Interior TI for medical offices ('Shrek Medical Offices' per Strata file). 10'-0" walls with ceiling lids (lids replace lay-in ceiling, take surface lighting + HVAC ducts). Existing hollow walls remain. Solid-fill new walls.

Work Scope

LÏEF/ACG labor + drywall+furring bid for interior partition wall install with 10'-0" hung-drywall lid. SABS material by Strata as pass-through (visible, no markup). Wall stack: 6" EPS + SABScrete + furring + 5/8" GWB both sides. Lid: furring + 5/8" GWB. Finish Level 4. Foam reinstall after MEP rough-in = $1,500 allowance (DIV 06A). LÏEF procures drywall (Strata never supplies drywall). Excluded: lid penetration cutouts, surface fixtures/HPC/duct boots, MEP rough-in, firestop — by other subs. Kanopi format (Mercury v1.3 design language).

Scope Summary

Interior tenant improvement labor bid: 10'-0" partition walls with lids (solid fill), 1,420 SF basis.

Internal Notes

Primary ContactVal Zavala (Xtrata)

SUBMITTED to Val 2026-06-05 (v2.2-Kanopi via email thread 19e4fdc9fccfa2da). Brand-correct Kanopi format (Succulent green, full Armstrong wordmark, Jost type, Mercury v1.3 layout). 6 pages: 5 client-facing + 1 INTERNAL scope-responsibility matrix (deletable). LÏEF/ACG $23,921 + Strata $16,793.64 = $40,715. Stage 2 (Plan-Takeoff, ±14% MoE). Finish Level 4. Foam-reinstall-after-MEP $1,500 allowance included. Brand standards canonical ref: ~/Desktop/OPERATIONS/brand-standards/BRAND-STANDARDS.md. Source: Email thread 19e4fdc9fccfa2da (5/22). Prospects/Medical-Center-Partition-Walls/PROJECT-INFO.md. Xtrata material estimate 5/14/26 = $16,793.64 (1,420 SF wall surface, 142 LF × 10' tall, 6" EPS).

Bid Versions

v1.0Jun 1, 2026

Initial labor-only bid. Canyon Corporate Rev2 rate parity with 1.40x/1.25x small-job multipliers and new lid scope. 142 LF wall + 1,200 SF assumed lid. Finish was Level 4 over SABScrete (no drywall hung).

$24,202

v1.1Jun 2, 2026

Scope change per Jesse 6/2 AM: replaced Level 4 finish over SABScrete with hung 5/8" GWB drywall (Canyon Rev2 firewall analog). Drywall material added as pass-through line at cost. Added Canyon $63/LF vs Medical Center $189/LF gap-decomposition page.

$26,914

+$2,712 vs v1.0

v1.2Jun 2, 2026

Major revision per Jesse 6/2 PM. Canyon v3 Rev3 template with Armstrong block + ACG logo + ROC#. Rates: SABS install $9.35/LF, SABScrete $2.35/SF, drywall+furring bundled $1.58/SF. Strata SABS pass-through visible. LIEF/ACG $22,139 + Strata $16,793.64 = $38,933 program. SUPERSEDED by v2.0-Kanopi format 2026-06-05; archived.

$38,933

+$12,019 vs v1.1

v2.0-KanopiJun 5, 2026

First Kanopi-format attempt. Off-brand bright green (#006B3F), wrong LIEF logo (saturated PNG), tiny Armstrong icon (no wordmark), redundant Project Summary + Project Overview. SUPERSEDED by v2.1-Kanopi same day.

$38,933

$0 vs v1.2

v2.1-KanopiJun 5, 2026

Brand-correct rebuild per Jesse 6/5 PM. SETUP FIX: created ~/Desktop/OPERATIONS/brand-standards/ with LIEF Brand Guide 2025 (Jimmy K. canonical source), BRAND-STANDARDS.md reference, and brand-correct logos. CHANGES: (1) Off-brand bright green (#006B3F) REPLACED with brand Succulent (#646c65) for ALL emphasis. (2) LIEF logo: SUCCULENT variant (matches Mercury v1.3, brand-correct). (3) Armstrong logo: full stacked logo with 'ARMSTRONG CONSTRUCTION GROUP' wordmark (was icon-only). (4) Project Summary + Project Overview COMBINED into single Page 2 (no more redundancy). (5) Parity Comp MOVED to deletable INTERNAL final page (brick paver banner: 'DELETE BEFORE SENDING'). (6) Open Questions consolidated onto Page 2 cost summary. Font: Helvetica fallback (Jost not installed; fallback chain: Jost → Helvetica Neue → Helvetica). SAME NUMBERS: $22,139 + $16,793.64 = $38,933. v2.0-Kanopi scuttled (same day). SUPERSEDED by v2.2-Kanopi 2026-06-05 (never sent to client).

$38,933

$0 vs v2.0-Kanopi

v2.2-KanopiJun 5, 2026

FINAL — issued + SUBMITTED to Val (Xtrata) via email 2026-06-05. Changes vs v2.1: (1) Finish RESTORED to Level 4 (was downgraded to Level 3 in v1.2/v2.1). (2) NEW foam-reinstall-after-MEP allowance $1,500 under DIV 06A (Jesse: 'we need to include that'). (3) Bid stages re-keyed Budgetary 18% / Plan-Takeoff 14% / Field-Verified 6% / Submitted 0% (was 20/10/5/0). (4) Strata REMOVED as signatory — material supplier only; bid addressed to project owner (Shrek Medical Offices). (5) GC/OHP formatting fix (proper Loggia bars, were floating/screwy). (6) Assumptions=Succulent header / Exclusions=Brick Paver header (color differentiation per Mercury v1.3). (7) Takeoff disclaimer relocated from Project Summary to top of Assumptions page (was bunched). (8) LÏEF/Armstrong business address 8271 E. Gelding Dr, Scottsdale AZ 85260 + ROC #339747 added to metadata + signature block (saved to BRAND-STANDARDS.md as bid boilerplate). (9) Parity comp REWRITTEN as line-by-line scope-responsibility matrix (v1.2/v2.1/v2.2 + responsible party) — INTERNAL, deletable Page 6. (10) Jost font installed + embedded (was Helvetica fallback). LÏEF/ACG $23,921 + Strata $16,793.64 = $40,715 program.

$40,715

+$1,782 vs v2.1-Kanopi