Filiberto's Restaurant — Avondale

SEC N Dysart Rd & E Indian School Rd

Latest Bid

$790,000

Square Footage

2,434

Units

Scope Class

Full Project

Plan Stage

Project Lifecycle

Received
Takeoff
Bidding
Submitted
Awarded
Start

Plans & Estimates

Notes & Correspondence

Adding a note also updates last-correspondence date for this project.

  1. Commercial full-project bid. Dedicated engagement session queued 2026-04-15 for takeoff and scope lock.

    Apr 15, 2026 · Jesse Fowler

Project Brief

2,434 SF A-2 restaurant + 330 SF patio at SEC N Dysart Rd & E Indian School Rd, Avondale (Shops at Ascend Lot 2). V-B sprinklered, drive-thru with bi-fold service window. Architect: Taylor:Fracasse (job 24-067). Issued For Permit 10.05.25.

Work Scope

Per Jesse's 2026-04-14 directive this is a complete conventional bid — NOT SABS. LÏEF is pricing the full Taylor:Fracasse permit set (Job 24-067) for a 2,434 SF V-B sprinklered QSR restaurant with drive-thru (plus 330 SF patio) at Shops at Ascend, Avondale: metal-stud framing, OSB sheathing, Western one-coat stucco, prefab roof trusses, full MEP, fire suppression, kitchen hood/walk-in/grease interceptor, site improvements. Preliminary estimate $785K from 3-sheet set; full plan set (structural, MEP, sections) required to harden.

Scope Summary

Complete conventional bid (per Jesse 2026-04-14) — NOT SABS. Metal stud framing + drywall + stucco as drawn on the Taylor:Fracasse permit set.

Internal Notes

Complete conventional bid per Jesse 2026-04-14 — NOT SABS. v1 preliminary estimate $785K ($323/SF) from 3-sheet set. GC TBD. Kitchen cooking equipment by Owner; GC covers hood, walk-in, grease interceptor. Drive-thru queuing lane 89 LF vs 96 LF code requirement flagged. Full plan set needed from Taylor:Fracasse to harden bid to +/-8%. Source: Filibertos-Avondale/PROJECT-INFO.md, BID-2026-04-16/ build script + PDF, TAKEOFF.md, COST-BREAKDOWN.md. Jesse directive 2026-04-14.

Bid Versions

v1 PRELIMINARYApr 16, 2026

Full-project conventional GC estimate from 3-sheet set (SP-1, A1-0, A5-0). 15 CSI divisions, $681,800 hard cost + 5% contingency + 1.5% insurance + builders risk + 8% GC fee. $322.51/SF. +/-15% band ($667K-$903K). NOT SABS per Jesse directive.

$785,000

v1 Preliminary Full-SABSApr 16, 2026

Preliminary full-SABS bid from 3-sheet set. +/-15% band. Filibertos-Avondale/BID-2026-04-16/.

$790,000

+$5,000 vs v1 PRELIMINARY